Work Party Update – 2nd April 2019

Tonight, we repaired a small section of carpet in the Church that we considered was about to become a trip hazard.…

Work Party Update – 26th March 2019

No work was carried out tonight as there are no jobs pending and we are still waiting for approval on what paint to use for the Vestibule area. …

Work Party Update – 19th March 2019

Replaced 2 bulbs outside the gents toilet and at the front door. Repainted patch in the Vestibule with what may be the original colour. At gallery door we have tried a very pale green. If original can’t be obtained, this is possibly a close match. Have left wet paint signs!…

Work Party Update – 12th March 2019

This evening we finished filling in the cracks at the front of the Church.…

Work Party Update – 5th March 2019

At the front of the Church, we filled in cracks with polyfilla. We were interrupted by the fire alarm going off. The engineer is coming tomorrow to resolve the problem. …

Work Party Update – 26th February 2019

Painting was completed around the windows in the gallery.…

Work Party Update – 19th February 2019

We continued to scrape and plaster the gallery.…

Work Party Update – 12th February 2019

Tonight we did some plastering work. …

Work Party Update – 5th February 2019

Tonight we carried out a survey of the premises to see what work needs to be done.…

Work Party Update – 29th January 2019

The gents toilet painting is now finished. Frezzer used to store ice cream for the pantomime was moved onto the stage. Spare fridge was moved into the Session Room. Cork notice board put back up between small hall door and Church library. All books removed from shelves in small hall and put under stage. the bookcase was then dismantled.…

Older posts «